Document Type | Date | Description |
---|---|---|
Order - Final | 09/09/1999 | Commission Order Adopting Recommended Decision, in Part, and Modifying Recommended Decision, In Part.
|
Transcript | 08/27/1999 | Transcript; Volume 2; August 25, 1999; pages 55-92. (Billing 11-2-99)
|
Comment | 08/19/1999 | Comments RE: Recommended Decision on behalf of U S WEST from Lisa Anderl. (Disk provided & posted)
|
Comment | 08/19/1999 | Comments RE: Recommended Decision on behalf of NEXTLINK from Gregory Kopta. (Received via e-mail & posted) (Hardcopy rec'd 8/19/99)
|
Letter | 08/13/1999 | Ltr. to all parties, RE: Request for Presentation by Commission Staff (Wednesday, August 25, 1999).
|
Order - Supplemental | 08/12/1999 | Sixth Supplemental Order; Recommended Decision; Schedule for Filing Written Comments; Notice of Open Public Meeting for Hearing Arguments of the Parties (August 25, 1999)
|
Order - Prehearing Conference | 07/28/1999 | Fifth Supplemental Order on Prehearing Conference.
|
Response | 07/14/1999 | Reply to Section 252(i) issues on behalf of NEXTLINK from Gregory Kopta. (Received via e-mail and posted) (Hardcopy rec'd 7/14/99)
|
Response | 07/08/1999 | Answer on Section 252(i) Issues on behalf of U S WEST from Lisa Anderl. (Disk provided & posted)
|
Notice of Hearing | 06/23/1999 | Third Supplemental Order; Procedural Determinations; Further Proceedings; Notice of Prehearing Conference (June 28, 1999)
|
Transcript | 06/09/1999 | Volume 1; June 7, 1999; Pages 1-54. (Billing 11-2-99)
|
Response | 05/24/1999 | Response to Jurisdictional Issues on behalf of NEXTLINK from Gregory Kopta. (Received via e-mail & posted) (Hardcopy rec'd 5/24/99)
|
Response | 05/12/1999 | Answer to NEXTLINK's Petition for Enforcement of Interconnection Agreement on behalf of U S WEST from Lisa Anderl. (Disk provided & posted)
|