UTC Case Docket Details

Docket Number 041570

Case Docket Details Table
Docket Number UE-041570
Advice
Company Puget Sound Energy
DBA
Filing Type Petition
Industry (Code) Electric (140)
Status Closed
Lead Staff Hank McIntosh
Filed Date 08/31/2004
Effective Date N/A
Summary Petition for review and approval of the Power Cost Adjustment Mechanism Annual Report.

Event History

  • 02/23/2005 -- Open Meeting
  • 02/09/2005 -- Open Meeting
  • 02/23/2005 -- Approved (The Commission approved the request to include an additional $10.9 million of the return on the Tenaska regulatory asset in allowed power costs in PCA Period 2 should be partially granted in the amount of $6,074,927, resulting in a revised customer portion of the power cost deferral of $5,163,266, including accrued interest. Also, the Company's amended 2004 PCA Report as filed should be rejected, but PSE should be authorized to refile its report consistent with the Commission's Order and the Commission should approve a properly modified report by letter from the Commission's executive secretary.)
  • 02/09/2005 -- Deferred
  • 08/31/2004 -- Open