Order - Final | 08/04/2008 | Notice of Finality.
|
Order - Initial | 07/11/2008 | Order 01 - Initial Order Approving and Adopting Settlement Agreement. |
Agreement | 07/03/2008 | Settlement Agreement, Narrative in Support of Settlement Agreement, Certificate of Service and Letter on behalf of Parties from Jennifer Cameron-Rulkowski.
|
Letter | 07/02/2008 | Letter to all parties from Marguerite E. Russell, re: status update. |
Notice | 06/26/2008 | Notice of Assignment of Presiding Officer. |
Letter | 06/04/2008 | Letter on behalf of Parties from Jennifer Cameron-Rulkowski, RE: Settlement in Principle. |
Response | 05/28/2008 | Replacement response of Shuttle Express, Inc., from Brooks E. Harlow. (via web portal) |
Response | 05/22/2008 | Response on behalf of Shuttle Express, Inc., from Brooks E. Harlow, RE: Response to Penalty Assessment. (via Web Portal) |
Report | 05/19/2008 | Staff investigation - Shuttle Express, Inc. |
Penalty Assessment | 04/28/2008 | Penalty Assessment issued to Shuttle Express, Inc. in the amount of $9,500. |
Letter | 04/25/2008 | Letter to Carole J. Washburn from Brooks E. Harlow on behalf of Shuttle Express, Inc., RE: Shuttle Express withdraws its confidential designation and permits the commission to post the redacted documents. (via web portal) (hard copy rec'd 04/28/2008) |
Response | 11/30/2007 | Response on behalf of Shuttle Express, Inc., from Brooks E. Harlow, RE: Corrected Responses for requested information dated October 23, 2007. (via e-mail) (hard copy rec'd 12/3/2007) |
Response | 11/21/2007 | Redacted Response on behalf of Shuttle Express, Inc., from Brooks E. Harlow, P.C., RE: Commission request for information dated October 23, 2007. (via e-mail) |