Document Type | Date | Description |
---|---|---|
Order - Other | 03/20/2023 | Order Approving Fully Negotiated Interconnection Agreement Amendment No. 5.
|
MAIN SERVICE LIST | 03/09/2023 | MAIN SERVICE LIST
|
Amendment | 03/09/2023 | Request for approval of the Fifth Amendment to an Interconnection Agreement between Qwest Corporation and Charter Fiberlink WA-CCVII, LLC. From Josie Addington. (via web portal) |
Order - Other | 06/14/2022 | Order Approving fully negotiated interconnection agreement amendment No 4.
|
Amendment | 03/23/2022 | Request for approval of the Fourth Amendment to an Interconnection Agreement between Qwest Corporation and Charter Fiberlink WA-CCVII, LLC, from Josie Addington. (via web portal)
|
Order - Other | 09/07/2021 | Order Approving Fully Negotiated Interconnection Agreement Amendment 3. |
Amendment | 08/20/2021 | Request for approval of the Third Amendment to an Interconnection Agreement between Qwest Corporation and Charter Fiberlink WA-CCVII, LLC, from Josie Addington. (via web portal) |
Order - Other | 08/03/2021 | Order Approving Fully Negotiated Interconnection Agreement Amendment 2. |
Amendment | 06/17/2021 | Request for approval of Second Amendment to an Interconnection Agreement between Qwest Corporation d/b/a CenturyLink QC and Charter Fiberlink WA-CCVII, LLC, from Josie Addington. (via web portal)
|
Order - Other | 06/15/2021 | Order Approving Fully Negotiated Interconnection Agreement Amendment 1. |
MASTER SERVICE LIST | 08/20/2021 | Master Service List |
Amendment | 04/30/2021 | Request for approval of First Amendment to an Interconnection Agreement between Qwest Corporation d/b/a CenturyLink QC and Charter Fiberlink WA-CCVII, LLC, from Josie Addington. (via web portal)
|
Order - Other | 09/08/2009 | Order 11 - Order Approving Interconnection Agreement |
Exhibit | 09/08/2009 | Exhibits JDW-1T - JDW-5C, JDW-7, PG-1T - PG-6, TD-1T - TD-3T, TD-6 - TD-10, TJG-1T - TJG-7, TJG-14, TJG-21, WRE-1T - WRE-5, WRE-8, WRE-9, WRE-12C, WRE-14, WRE-16, PL-1T - PL-10, PL-12, PL-14, PL-15, RHW-1T - RHW-13, RA-1T - RA-13, and Hearing Exhibits HE-1 - HE-5 admitted. Exhibits TD-4 and TD-5 withdrawn. |
Replacement Page | 09/02/2009 | Errata Page 105 to the Arbitrated Interconnection Agreement on behalf of Qwest from Lisa A. Anderl. (via e-mail) (hard copy rec'd 9/03/2009) |
Compliance | 08/24/2009 | Arbitrated Interconnection Agreement between Qwest Corporation and Charter Fiberlink on behalf of Qwest Corporation from Lisa A. Anderl. (via e-mail) (hard copy rec'd 8/24/2009)
|
Order - Final | 07/23/2009 | Order 10 - Final Order Denying Charter's Petition For Administrative Review; Denying Qwest's Petition For Review; and Affirming, With One Clarification, Arbitrator's Report and Decision. |
Order - Other | 07/10/2009 | Order 09 - Order Modifying Procedural Schedule. |
Letter | 07/10/2009 | Letter to David W. Danner from K.C. Halm on behalf of Charter Fiberlink WA-CCVII, LLC, RE: Charter consents to a one week extension in the entry of the Commission's Order. (via web portal) (hard copy rec'd 7/13/2009) |
Letter | 07/09/2009 | Letter to David Danner from Lisa A. Anderl on behalf of Qwest Corporation, RE: Qwest consents to a one week extension in the entry of the Commission's order. (via e-mail) (hard copy rec'd 7/10/2009) |
Transcript | 06/30/2009 | Transcript Volume 4; June 16, 2009; Pages 366-421.
|
Notice | 05/22/2009 | Notice of Oral Argument of the Parties on Petition for Review (Tuesday, June 16, 2009, at 9:30 a.m.) |
Response | 05/18/2009 | Reply to Petition for Administrative Review of Arbitrator's Report and Decision on behalf of Charter Fiberlink WA-CCVII, LLC, from Mary A. Scarsorie. (via e-mail) (hard copy rec'd 5/19/2009)
|
Response | 05/18/2009 | Answer to Charter's Petition for Commission Review of Arbitrator's Report and Decision, Order 07, on behalf of Qwest Corporation from Lisa A. Anderl. (via e-mail) (hard copy rec'd 5/19/2009) |
Petition | 05/06/2009 | Petition for Commission Review of Arbitrator's Report and Decision, Order 07, including Attachment A, on behalf of Qwest Corporation from Lisa A. Anderl. (via e-mail) (hard copy rec'd 5/07/2009)
|
Petition | 05/06/2009 | Petition for Administrative Review of Arbitrator's Report and Decision on behalf of Charter Fiberlink WA-CCVII, LLC, from Mary A. Scarsorie. (via e-mail) (hard copy rec'd 5/07/2009)
|
Order - Other | 04/28/2009 | Order 08 - Order Granting Request to Modify Procedural Schedule (Petitions for Review now due, Wednesday, May 6, 2009) (Replies to Petitions for Review now due, Monday, May 18, 2009) |
Letter | 04/27/2009 | Letter to David Danner from Lisa A. Anderl on behalf of Qwest Corporation and Charter Fiberlink WA-CCVII, LLC, RE: Request for Extension of Filing Deadlines. (via e-mail) (hard copy rec'd 4/28/2009) |
Order - Other | 03/30/2009 | Order 07 - Arbitrator's Report and Decision |
Brief | 02/17/2009 | Reply Brief on behalf of Qwest Corporation from Lisa A. Anderl. (via e-mail) (hard copy rec'd 2/18/2009) |
Brief | 02/17/2009 | Reply Brief on behalf of Charter Fiberlink WA-CCVII, LLC, from Gregory Kopta. (via e-mail) (hard copy rec'd 2/18/2009) |
Notice | 01/30/2009 | Notice Extending Deadline For Filing Joint Issues Matrix (Due on or before Tuesday, February 17, 2009) |
Brief | 01/30/2009 | Redacted Replacement Table of Contents for Opening Briefs on behalf of Charter Fiberlink WA-CCVII, LLC, from Mary Scarsorie. (via e-mail) (hard copy rec'd 2/02/2009) |
Letter | 01/29/2009 | Letter to Lisa Anderl from Marguerite E.Friedlander, re: Hearing Transcript Volume III |
Letter | 01/29/2009 | Letter on behalf of Qwest Corporation from Lisa Anderl, RE: Revised Issues Matrix. (via e-mail) |
Brief | 01/29/2009 | Redacted Opening Brief on behalf of Charter Fiberlink WA-CCVII, LLC, from Mary Scarsorie. (via e-mail) (hard copy rec'd 1/30/2009) |
Brief | 01/29/2009 | Opening Brief on behalf of Qwest Corporation from Lisa Anderl. (via e-mail) (hard copy rec'd 1/30/2009) |
Letter | 01/08/2009 | Letter on behalf of Qwest Corporation from Maura Peterson, RE: Hearing Exhibit List. (via e-mail) (hard copy rec'd 1/09/2009) |
Transcript | 01/05/2009 | Transcript Volume 3, December 17, 2008, Pages 192-365.
|
Transcript | 01/05/2009 | Transcript Volume 2, December 16, 2008, Pages 13-191.
|
Notice | 01/05/2009 | Notice of Substitution of Counsel on behalf of Charter Fiberlink WA-CCVII, LLC, from K.C. Halm (via web portal)
|
Order - Other | 12/31/2008 | Order 06 - Order Granting Request to Modify Procedural Schedule (Post hearing opening briefs now due, Thursday, January 29, 2009) (Post hearing closing briefs now due, Tuesday, February 17, 2009). |
Letter | 12/30/2008 | Letter to Dave Danner from Lisa Anderl on behalf of Qwest Corporation, RE: Modification of Post-Hearing Schedule. (via e-mail) (hardcopy rec'd 1/02/2009) |
Exhibit | 12/26/2008 | Charter Fiberlink's Revised and Redacted Confidential Exhibits from Maura Peterson. (via e-mail) (hard copy rec'd 1/02/2009) |
12/24/2008 | E-mail to Greg Kopta and Lisa Anderl, from Marguerite Russel, RE: Request for Extension of Filings. (posted) | |
Exhibit | 12/15/2008 | Charter Fiberlink's Non-Confidential list of Cross Examination Exhibits, Pre-filed Exhibits and Order of Witnesses from Gregory Kopta. (via e-mail) (hard copy rec'd 12/15/2008)
|
Order - Other | 12/12/2008 | Order 05, Order Granting Request to Modify Procedural Schedule (Witness Lists and disclosure of cross examination exhibits now due Friday, December 12, 2008) |
Exhibit | 12/11/2008 | Qwest's Non-Confidential list of Cross Examination Exhibits, Pre-filed Exhibits and Order of Witnesses from Maura Peterson. (via e-mail) (hard copy rec'd 12/12/2008)
|
12/11/2008 | E-mail to Marguerite Russell, et al, from Greg Kopta on behalf of Charter Fiberlink, RE: Request for Extension of Filing. (posted)
|
|
Confidentiality Agreement | 12/09/2008 | Confidentiality Agreement of Anne Solwick on behalf of Staff from Elizabeth M. DeMarco. |
Confidentiality Agreement | 12/02/2008 | Confidentiality Agreements for Mary Ann Neill and Jason Topp on behalf of Qwest Corporation from Maura Peterson. (scanned & posted) |
Confidentiality Agreement | 11/25/2008 | Highly Confidential Agreement for Clifford Williams on behalf of Charter Fiberlink from Gregory Kopta. (via e-mail) (hard copy rec'd 11/26/08)
|
Confidentiality Agreement | 11/25/2008 | Confidentiality Agreement of Clifford Williams on behalf of Charter Fiberlink from Gregory Kopta. (via e-mail) (hard copy rec'd 11/26/08)
|
Testimony | 11/17/2008 | Redacted Rebuttal Testimony and Exhibits on behalf of Qwest Corporation from Lisa A. Anderl. (via e-mail) (hard copy rec'd 11/18/08)
|
Testimony | 11/17/2008 | Non-Confidential version of Rebuttal Testimony of James D. Webber, Timothy J. Gates, Peggy Giaminetti, and Allison Cosway on behalf of Charter Fiberlink WA-CCVII, LLC, from Gregory J. Kopta. (via e-mail) (hard copy rec'd 11/18/08)
|
Confidentiality Agreement | 11/13/2008 | Confidentiality Agreements for Billy H. Pruitt, Patrick Phipps, and Timothy J. Gates, on behalf of Charter Fiberlink WA - CCVII, LLC, from Mary Scarsorie. (via e-mail) (hard copy rec'd 11/14/08) |
Order - Other | 11/12/2008 | Order 04 - Order Granting Request to Amend Procedural Schedule (Responsive Testimony now due November 17, 2008). |
Letter | 11/10/2008 | Letter on behalf of Charter Fiberlink WA-CCVII, LLC, from Gregory J. Kopta, RE: Request for extension of time to file responsive testimony. (via e-mail) (hard copy rec'd 11/12/08) |
Testimony | 11/06/2008 | Corrected Direct Testimony of Renee Albersheim on behalf of Qwest Corporation from Maura E. Peterson. (via e-mail) (hard copy rec'd 11/10/08)
|
Testimony | 10/15/2008 | Direct Testimony of Timothy J. Gates on behalf of Charter Fiberlink WA CCVII, LLC from Mary A. Scarsorie, RE: Page 61 which was advertently left out of October 8, 2008 filing. (scanned & posted)
|
Replacement Page | 10/14/2008 | Corrected Direct Testimony of Timothy J. Gates on behalf of Charter Fiberlink WA-CCVII, LLC from Mary Scarsorie. (via e-mail) |
Testimony | 10/08/2008 | Direct Testimony of William R. Easton, Robert H. Weinstein, Renee Albersheim and Philip Linse on behalf of Qwest Corporation from Maura E. Peterson. (via e-mail)
|
Testimony | 10/08/2008 | Direct Testimony of Timothy J. Gates, Michael Starkey, Allison Cosway and Peggy Giaminetti on behalf of Charter FiberLink WA-CCVII, LLC from Mary Scarsorie. (via e-mail) (hard copy rec'd 10/9/2008)
|
Confidentiality Agreement | 10/02/2008 | Confidential Agreements of Lisa Anderl, Thomas Dethlefs, Maura Peterson and Lori White, Expert Agreements of William Easton, Renee Albersheim, Philip Linse, and Mark Reynolds, and Highly Confidential Agreements of Philip Linse, Lisa Anderl, Maura Peterson, Lori White, Mark Reynolds and Thomas Dethlefs on behalf of Qwest Corporation from Maura Peterson. (via e-mail) (hard copy rec'd 10/6/2008) |
Transcript | 09/24/2008 | Transcript Volume 1, September 10, 2008, Pages 1-12.
|
Confidentiality Agreement | 09/24/2008 | Confidential and Highly Confidential Agreements signed by Chris Rose on behalf of Commission Staff from Elizabeth M. DeMarco, Legal Assistant. |
Confidentiality Agreement | 09/19/2008 | Confidentiality Agreements of Gregory J. Kopta, Brian A. Nixon and K.C. Halm, and Highly Confidential Agreement of Gregory J. Kopta on behalf of charter Fiberlink from Gregory J. Kopta. (via e-mail) (hard copy rec'd 09/22/08) |
Order - Protective | 09/17/2008 | Order 03 - Protective Order with "Highly Confidential" Provisions |
Order - Prehearing Conference | 09/17/2008 | Order 02 - Prehearing Conference Order; Notice of Hearing (Set for December 16-18, 2008) |
Letter | 09/15/2008 | Letter on behalf of Qwest Corporation from Lisa A. Anderl, RE: Qwest waives the statutory deadline for an Arbitrator's report. (via e-mail) (hard copy rec'd 09/16/2008) |
Letter | 09/11/2008 | Letter on behalf of Charter Fiberlink WA-CCVII, LLC from Gregory J. Kopta, RE: Charter agrees to waive the statutory dealine for an arbitrator's report. (via e-mail) (hard copy rec'd 09/12/2008) |
Response | 09/02/2008 | Answer on behalf of Qwest Corporation from Lisa A. Anderl, RE: Charter Fiberlink, LLC's Arbitration Petition. (scanned & posted) |
Order - Other | 08/15/2008 | Order 01 - Order on Arbitration Procedure; Appointment of Arbitrator; Notice of Prehearing Conference (Set for September 10, 2008, at 1:30 p.m.) |
Initial Filing | 08/08/2008 | Initial filing on behalf of Charter Fiberlink WA-CCVII, LLC from Gregory J. Kopta. (via e-mail) (hard copy rec'd 08/08/2008)
|