Document Type | Date | Description |
---|---|---|
Memorandum | 07/07/2011 | Memorandum from Kathy Hunter to File, RE: GCPF project complete. |
Agreement | 06/24/2011 | Signed Project Agreement on behalf of Eastern WA Gateway Railroad from John Howell. (scanned & posted) |
Order - Other | 06/15/2011 | Order 02 - Order Granting Additional Expenditure from the Grade Crossing Protective Fund and Extension of Time to Complete Project and Submit Request for Reimbursement. |
06/13/2011 | Email to Kathy Hunter, from John Howell, Eastern Washington Gateway RR, RE: Extension request. (scanned & posted) | |
Order - Final | 04/29/2011 | Order 01 - Order Granting Petition to Upgrade Active Warning Devices and Authorizing Expenditure from the Grade Crossing Protective Fund.
|
Initial Filing | 04/19/2011 | Initial filing on behalf of Eastern Washington Gateway Railroad, from John Howell. (scanned and posted)
|