UTC Case Docket Details

Docket Number 132043

Case Docket Details Table
Docket Number UE-132043
Advice
Company Puget Sound Energy
DBA
Filing Type Staff Investigation
Industry (Code) Electric (140)
Status Closed
Lead Staff Cebulko, Bradley (UTC)
Filed Date 10/31/2013
Effective Date N/A
Summary NOTE: This item will be heard on Friday, August 12, 2016, at 9:30 a.m., in the Commission's Hearing Room 206. Electric 2014-2015 Biennial Conservation Report.

Event History

  • 08/12/2016 -- Close (Commissioner Rendahl moved to issue an Order in Docket UE-132043 finding that: (1) Puget Sound Energy has complied with reporting requirements pursuant to WAC 480 109 120 and RCW 19.285.070. (2) Puget Sound Energy has complied with Order 01 in Docket UE 132043. (3) Puget Sound Energy has achieved 552,596 megawatt-hours of conservation during the 2014-2015 biennium. (4) Puget Sound Energy has applied 27,920 megawatt-hours of conservation during the 2014-2015 biennium towards satisfying its decoupling conservation commitment. (5) Puget Sound Energy has achieved 38,906 megawatt-hours of excess conservation during the 2014-2015 biennium. Commissioner Jones seconded the motion. The motion carried (3:0) )
  • 08/04/2016 -- Open Meeting (NOTE: This item will be heard on Friday, August 12, 2016, at 9:30 a.m., in the Commission's Hearing Room 206.)
  • 10/29/2015 -- Continued (Allowed to become effective per Consent Agenda.)
  • 10/29/2015 -- Open Meeting
  • 04/30/2015 -- Continued (Allowed to become effective per the No Action Agenda. )
  • 04/30/2015 -- Open Meeting
  • 12/30/2014 -- Continued (Published on the No Action Agenda, but kept open per request of Juliana Williams.)
  • 12/01/2014 -- Re-open (Per request of Juliana Williams.)
  • 12/30/2014 -- Open Meeting
  • 09/11/2014 -- Allowed (Disposition: Commissioner Goltz moved that: 1) Puget Sound Energy’s 2014-2015 decoupling conservation commitment be established at 27,920 MWh above its biennial conservation target of 485,770 MWh. 2) Puget Sound Energy is required to perform its decoupling conservation commitment for the full duration of the 2014-2015 biennium and for any biennium during which its approved decoupling program is in effect. 3) Should PSE’s decoupling program be terminated or withdrawn prior to the end of a biennium, PSE will exceed its commission-approved biennial conservation target by five percent (5%) through the full biennium. Commissioner Jones seconded the motion. The motion carried (3:0))
  • 09/11/2014 -- Open Meeting
  • 08/28/2014 -- Re-open
  • 12/12/2013 -- Open Meeting (NOTE: This item will be heard on Wednesday, December 18, 2013, at 9:00 AM in the Commission's Hearing room, Room 206.)
  • 12/18/2013 -- Approved (Commissioner Jones moved to issue an order approving Puget Sound Energy's (PSE's) 10-year conservation potential of 2,730,408 megawatt-hours (MWh) and biennial conservation target of 485,770 MWh, subject to the conditions in Attachment a, and suspending the First Revision of WN U-60, Tariff G, Sheet 292-A, and allowing all other tariff revisions filed by PSE in Docket UE-132032 to take effect January 1, 2014, by operation of law. Commissioner Goltz seconded the motion. The motion carried (3:0))
  • 10/31/2013 -- Open