UTC Case Docket Document Sets

Filing UE - 160353

 

Document Type Date Description
Letter 07/08/2019 2017 IRP and 2019 IRP Acknowledgement Letter.
Response 06/11/2018 Response to the 2017 Integrated Resource Plan Acknowledgement Letter, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal) (hard copies rec'd 06/12/18)
Letter 05/07/2018 2017 Electric IRP Acknowledgment Ltr
Replacement Page 05/07/2018 Replacement Page for the 2017 Integrated Resource Plan Update, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal) (hard copies rec'd 05/08/18)
Plan 05/01/2018 2017 Integrated Resource Plan Update, on behalf of Pacific Power & Light Company, from Ariel Son. (via web portal) (hard copies rec'd 05/02/18)
Letter 03/26/2018 Letter RE: 2017 Integrated Resource Plan Update Timing, on behalf of Pacific Power & Light Company, from Ariel Son. (via web portal) (hard copies rec'd 03/27/18)
Recording 07/11/2017 Recessed Open Meeting Held on June 29, 2017.
Document 02/27/2018 Redacted Request for Acknowledgement of 2017 Request for Proposals Final Shortlist and Independent Evaluator Closing Report, on behalf of Pacific Power & Light Company, from Ariel Son. (via web portal)(hard copies rec'd 02/28/18)
Letter 11/15/2017 Letter RE: Update to Solar Request for Proposals, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal) (hard copies rec'd 11/16/17)
Letter 10/04/2017 Letter RE: the Public Utility Commission of Oregon's order amending the conditional approval of PacificiCorp's 2017 Renewable Request for Proposals, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)(hard copies rec'd 10/05/17)
Document 09/15/2017 Public Utility Commission of Oregon's conditional approval of the 2017 Renewable Request for Proposals, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal) (hard copies rec'd 09/18/17)
Workpapers 08/15/2017 Redacted Workpapers, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)
Workpapers 08/15/2017 Non-confidential Workpapers, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)
Report 08/15/2017 Energy Vision 2020 Update for the 2017 Integrated Resource Plan, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)(hard copies rec'd 08/16/17)
Document 08/11/2017 Independent Evaluator Report for 2017 IRP, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)(hard copies rec'd 08/14/17)
Document 08/04/2017 Draft of 2017 Renewable Request for Proposals, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)(hard copies rec'd 08/07/17)
Replacement Page 07/10/2017 Revised Presentation for the recessed open meeting on July 11, 2017, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)
Presentation 07/07/2017 Presentation for the recessed open meeting on July 11, 2017, on behalf of Pacific Power & Light Company, from Etta Lockey. (via web portal)(hard copies rec'd 07/10/17)
Comment 06/23/2017 Supplement to Comments, on behalf of National Grid USA, from Jack Stoddard. (via web portal)
Comment 06/16/2017 Comments, on behalf of Renewable Northwest, from Michael O'Brien. (via email)
Comment 06/16/2017 Comments, on behalf of the Renewable Energy Coalition, on behalf of John Lowe. (via email)
Comment 06/16/2017 Comments, on behalf of Northwest and Intermountain Power Producers Coalition, from Irion Sanger. (via email)
Comment 06/16/2017 Comments, on behalf of NW Energy Coalition, from Fred Heutte. (via email)
Comment 06/16/2017 Comments, on behalf of the Industrial Customers of Northwest Utilities, from Haley Thomas. (via web portal)
Comment 06/16/2017 Comments on behalf of National Grid USA, from Nathan Sandvig. (via web portal)
Notice 04/27/2017 Notice of Opportunity to File Written Comments (By Friday, June 16, 2017) and Notice of Recessed Open Meeting (To be held at 9:30 a.m., Tuesday, July 11, 2017)
Replacement Page 04/11/2017 2017 Integrated Resource Plan Replacement Pages, on behalf of Pacific Power & Light Company, from R. Bryce Dalley. (via web portal)(hard copies rec'd 04/12/17)
Plan 04/04/2017 2017 Integrated Resource Plan, on behalf of Pacific Power & Light Company, from R. Bryce Dalley. (via web portal)(hard copies rec'd 04/05/17)
Order - Final 03/29/2017 Order 01 Order Granting Temporary Exemption From Rule.
Replacement Page 03/21/2017 2017 IRP Work Plan Replacement Sheet, on behalf of Pacific Power & Light Company, from R. Bryce Dalley. (via web portal) (hard copy rec'd 3/22/17)
Petition 03/17/2017 Petition to Request Extension to File 2017 Integrated Resource Plan, on behalf of Pacific Power & Light Company, from R. Bryce Dalley. (via web portal)(hard copies rec'd 03/20/17)
Initial Filing 03/30/2016 2017 Integrated Resource Plan Work Plan, on behalf of Pacific Power & Light, from R. Bryce Dalley. (via web portal)