Document Type | Date | Description |
---|---|---|
Memorandum | 12/06/2018 | Closing memo to file |
Agreement | 10/18/2018 | Signed second revised project agreement from Joe Welsh for City of Auburn. |
Order - Other | 10/04/2018 | Order Granting Extension of Time to Complete Project and Submit Request for Reimbursement. |
09/27/2018 | Second request for extension of time to complete project and request reimbursement, from Joe Welsh for City of Auburn. | |
Agreement | 06/15/2018 | Signed revised project agreement from City of Auburn. |
Order - Other | 06/13/2018 | Order Amending Commission Order 01 and Authorizing Additional Disbursement from the Grade Crossing Protective Fund and Granting Extension of Time to Complete Project
|
Document | 06/04/2018 | Request to increase the grant amount and extend the project completion, on behalf of the City of Auburn, from Joe Welsh. (via email) |
Agreement | 05/24/2018 | Signed project agreement from City of Auburn. |
Order - Final | 04/12/2018 | Order 01 Order Granting Request for Disbursement From the Grade Crossing Protective Fund.
|
MASTER SERVICE LIST | 03/21/2018 | MASTER SERVICE LIST |
Initial Filing | 03/21/2018 | Application for disbursement of funds from the Grade Crossing Protective Fund, on behalf of the City of Auburn, from Joseph Welsh. (via email) |