Document Type | Date | Description |
---|---|---|
Memorandum | 12/19/2018 | Closing memo to file. |
Agreement | 10/19/2018 | Signed second revised project agreement from Joe Welsh for City of Auburn |
Order - Other | 10/17/2018 | Order Granting Additional Extension of Time to Complete Project and Submit Request for Reimbursement. |
10/15/2018 | Second request for extension of time to complete project and request reimbursement from the GCPF from Scott Nutter at City of Auburn. | |
Replacement Page | 08/22/2018 | Revised Project Agreement from the City of Auburn. |
Order - Other | 08/16/2018 | Order Granting Extension of Time to Complete Project and Submit Request for Reimbursement. |
08/16/2018 | Request for extension of time to complete project and submit request for reimbursement from the City of Auburn. | |
Agreement | 05/24/2018 | Signed project agreement from City of Auburn. |
Order - Final | 04/12/2018 | Order 01 Order Granting Request for Disbursement From the Grade Crossing Protective Fund.
|
MASTER SERVICE LIST | 04/02/2018 | MASTER SERVICE LIST |
Initial Filing | 04/02/2018 | Application for disbursement of funds from the Grade Crossing Protective Fund, on behalf of the City of Auburn, from Joseph Welsh. (via email) |