UTC Case Docket Document Sets

Filing UG - 180608

 

Document Type Date Description
Compliance 12/10/2019 Revised 2019 Integrated Resource Plan Progress Report, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)
Order - Final 11/07/2019 Order 02, Granting Petition.
Comment 11/06/2019 Comments, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)
Comment 11/05/2019 Comments from Michael Laurie. (via email)
Comment 11/05/2019 Comments from Terry Sullivan. (via email)
Comment 11/05/2019 Comments from Diane Emerson. (via email)
Open Meeting Memo 11/07/2019 Open Meeting Memo for the November 07, 2019 Open Meeting.
Response 11/01/2019 Response to Staff Petition for Exemption, on behalf of Public Counsel, from Lisa Gafken. (via web portal)
Petition 10/28/2019 Commission Staff’s Petition for and Order Granting Exemption From WAC 480-100-238(4) and (5) from Nash Callaghan
Comment 10/03/2019 Comments, on behalf of the Vashon Climate Action Group, from Stephanie Barbee, Rob Briggs, Suzanne Greenberg, Andy James, Kevin Jones, Virginia Lohr, Noah Roselander, Maia Syfers and Judy Twedt. (via email)
Comment 10/03/2019 Comments, on behalf of Coalition of Eastside Neighborhoods for Sensible Energy (CENSE), from Don Marsh. (via email)
Letter 09/26/2019 Letter from Mark L. Johnson, top 2019 PSE IRP TAG Members.
Letter 09/04/2019 TAG Response to Energize Eastside.
Letter 03/27/2019 Compliance Acknowledgment Letter re IRP Work Plan
Letter 03/15/2019 Puget Sound Energy's compliance with Order 01.
Compliance 02/28/2019 2019 Integrated Resource Plan Work Plan Revision Pursuant to Order 01 Updates to Appendix A, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)
Order - Final 02/15/2019 Order 01 Order Granting Petition Subject to Condition.
Open Meeting Memo 02/15/2019 Open Meeting Memo for the February 15, 2019, Open Meeting.
Comment 02/07/2019 Comments of PSE IRP TAG meeting, from Chris Chapin. (via email)
Comment 02/07/2019 Comments of PSE IRP TAG meeting, from Radka Chapin. (via email)
Comment 02/07/2019 Comments of PSE IRP TAG meeting, from Hoa Pantastico. (via email)
Amendment 02/04/2019 Amended Petition to extend the filing date of its 2019 Integrated Resource Plan from July 15, 2019 to January 15, 2020, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)
Petition 02/01/2019 Petition to extend the filing date of its 2019 Integrated Resource Plan from July 15, 2019 to January 15, 2020, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)
Replacement Page 12/19/2018 Revised Appendix A, on behalf of Puget Sound Energy, from Jon Piliaris. (via email)
Replacement Page 10/15/2018 Updated Appendices for its 2019 Integrated Resource Plan Work Plan, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)
MASTER SERVICE LIST 02/15/2019 Master Service List
Initial Filing 07/13/2018 2019 Integrated Resource Plan Work Plan, on behalf of Puget Sound Energy, from Jon Piliaris. (via web portal)