Document Type | Date | Description |
---|---|---|
Order - Final | 09/10/2020 | Order 02 Regarding Conservation Achievement for the 2018-2019 Biennium.
|
Open Meeting Memo | 09/10/2020 | Open Meeting Memo for the September 10, 2020, Open Meeting. |
Replacement Page | 08/17/2020 | Revised Appendix A, on behalf of Avista Corporation d/b/a Avista Utilities, from Shawn Bonfield. (via web portal) |
Comment | 08/06/2020 | Staff Comments from Nash Callaghan. |
Comment | 07/23/2020 | Comments from Jon Powell. (via email) |
MAIN SERVICE LIST | 06/05/2020 | MAIN SERVICE LIST |
Notice | 06/04/2020 | Notice of Opportunity Comment and Notice of Open Meeting. |
Report | 05/29/2020 | 2018-2019 Biennial Conservation Report (BCR) and 2019 Annual Conservation Report (ACR), on behalf of Avista Corporation d/b/a Avista Utilities, from Shawn Bonfield. (via web portal)
|
Open Meeting Memo | 08/08/2019 | Open Meeting Memo for the August 8, 2019, Open Meeting. |
Report | 06/19/2019 | Report on 2018 Washington State Investor Owned Utility Energy Efficiency Joint Advisory Group Activities and Outcomes, on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal)
|
Report | 05/30/2019 | 2018 Annual Conservation Report (ACR), on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal) |
Agreement | 12/06/2018 | Redacted Customer Agreements, Appendices N through S, on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal) |
Agreement | 12/04/2018 | Redacted Customer Agreements, Appendices A through M, on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal)
|
Compliance | 11/15/2018 | 2019 Electric Annual Conservation Plan and Tariff Revision Schedule 90, on behalf of Avista Corporation d/b/a/ Avista Utilities, from Linda Gervais. (via web portal)
|
Order - Other | 01/12/2018 | Order 01, Accepting Avista Corporation's Calculation of its 2018-2019 Biennial Conservation Target; Imposing Conditions; Authorizing and Requiring Compliance Filing
|
Replacement Page | 01/11/2018 | Revised 2018-2019 Biennial Conservation Plan Target, on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal)
|
Comment | 01/05/2018 | Comments RE: Avista Corporation's Low-Income Fuel Conversion, on behalf of The Energy Project, from Shawn Collins. (via web portal) (hard copies rec'd 01/09/18) |
Notice | 01/05/2018 | Notice of Intent to Address fuel Conversion Program in Pending General Rate Case Proceeding |
Comment | 12/27/2017 | Commission Staff’s Reply to Stakeholder Comments Regarding NEEA Savings, from Andrew J. O'Connell |
Notice | 12/20/2017 | Notice of Change to Scheduled Recessed Open Meeting (Now set for Wednesday, January 10, 2018, at 2:00 p.m.) and Notice of Potential Ex Parte Communication. (NOTE: Unable to email on 12/19/17 due to technical problems) |
Comment | 12/19/2017 | Comments RE: Response to Staff's Comments Regarding Electric Utility Conservation Plans Under the Energy Independence Act, on behalf of Public Counsel, from Carla Colamonici. (via email) |
Comment | 12/18/2017 | Comments RE: Commission Staff Comments of Electric Utility Conservation Plans Under the Energy Independence Act, on behalf of Avista Corporation d/b/a Avista Utilities, Puget Sound Energy and Pacific Power & Light Company, from Dan Johnson, Dan Anderson and Don Jones. (via web portal)
|
Open Meeting Memo | 12/20/2017 | Recessed Open Meeting Memo from the December 14, 2017 meeting, being held on December 20, 2017.
|
Replacement Page | 12/07/2017 | Revisions to the 2018-2019 Biennial Conservation Plan and the 2018 DSM Annual Conservation Plan, on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal) |
Notice | 12/04/2017 | Notice of Potential Ex Parte Communication |
Comment | 12/01/2017 | Comments RE: Avista's Ten-Year Achievable Conservation Potential, Biennial Conservation Target and Biennial Conservation Plan for 2018-2019, on behalf of NW Energy Coalition, from Amy Wheeless. (via email) (hard copies rec'd 12/6/17) |
Comment | 12/01/2017 | Comments RE: Avista Corporation's Electric Biennial Conservation Plan, on behalf of Public Counsel, from Carla Colamonici. (via web portal) |
Comment | 12/01/2017 | Comments RE: Avista Corporation's Biennial Conservation Plan, on behalf of Utility Conservation Services, LLC, from Thomas Eckhart. (via web portal) |
Comment | 12/01/2017 | 2018-2019 Biennial Conservation Plan Comments, on behalf of Staff, from Andrew J. O'Connell |
Comment | 11/30/2017 | Comments, on behalf of The Energy Project, from Shawn Collins. (via web portal) |
Comment | 11/29/2017 | Comments RE: Avista Utilities 2018-2019 Biennial Conservation Plan and 2018-2027 Achievable Conservation Potential, from Jon Powell. (via email) |
Notice | 11/06/2017 | Notice of Opportunity to Comment on Avista Corporation's Report Identifying its Ten-Year Achievable Conservation Potential and its Biennial Conservation Target Pursuant to RCW 19.285.040 and WAC 480-109-120 (Comments due by Friday, December 1, 2017) and Notice of Recessed Open Meeting (To be Held at 1:30 p.m., Thursday, December 20, 2017)
|
Initial Filing | 11/01/2017 | Biennial Conservation Plan for 2018-2019, on behalf of Avista Corporation d/b/a Avista Utilities, from Linda Gervais. (via web portal)
|